If A works for 3 days and B works for 2 days, they complete of work. If A works for 2 days and B works for 3 days, they complete of work. How many days does A take to complete the work alone?
A, B, and C can complete a work in 6 days, 8 days, and 12 days respectively. A and B work for 2 days, then C joins them. How many more days will they take to complete the remaining work?
A contractor agrees to build a bridge in 300 days. He employs 10 workers. After 150 days, he finds that only half the work is complete. How many additional workers does he need to finish on time?
X and Y can complete a task in 8 days. Y and Z can complete it in 12 days. X and Z can complete it in 16 days. How many days will X alone take?
A merchant sells two items for ₹500 each. On one he gains 25% and on the other he loses 25%. What is his overall profit or loss percentage?
A man can row 40 km downstream and 24 km upstream in 8 hours. The next day he rows 24 km downstream and 40 km upstream in 9 hours. Find the speed of boat in still water.
A's efficiency is 20% more than B's. If both work together for 5 days and then A leaves, B completes remaining work in 5 more days. In how many days can A complete the work alone?
A train passes two persons in 5 seconds and 8 seconds respectively. If their speeds are 10 m/s and 8 m/s respectively, find the train's length.
A contractor undertakes to build a road in 75 days with 40 workers. After 25 days, only of the road is completed. How many additional workers are needed to complete the road on time?
If 15 workers can dig 10 wells in 8 days, how many workers are needed to dig 4 wells in 6 days?
A and B start a business with ₹10,000 and ₹15,000 respectively. After 8 months, C joins with ₹12,000. At the end of the year, profit is ₹11,400. How much profit does A get?
A shopkeeper marks items 60% above cost. He gives 10% discount on marked price and an additional 5% discount on the discounted price. What is his net profit percentage?
Three pipes A, B, C can fill a tank in 6, 8, 12 hours respectively. If A and B are opened for 2 hours, then A is closed and C is opened, in how many more hours will the tank be filled?
A boat can cover 45 km downstream and 27 km upstream in 9 hours. If the speed of current is 3 km/h, find the speed of boat in still water.
A contractor undertakes a project for ₹1,00,000 to be completed in 100 days. For every day of delay, he loses ₹500. If he completes in 110 days, what is his net income?
A piece of work can be done by 12 men in 16 days. If 4 men leave after 6 days, how many more days are needed to complete the work?
Two pipes A and B fill a tank in 12 and 15 hours respectively. A third pipe C empties it in 20 hours. If all three are opened, in how many hours will the tank be full?
A sells an article to B at 20% profit. B sells it to C at 10% loss. If C pays ₹1080, what is A's cost price?
A man invests ₹1000 at 10% SI for 3 years and ₹2000 at 12% SI for 2 years. What is his total return?
Two men A and B can do a job in 30 and 40 days respectively. They work together for 10 days, then A leaves. In how many days will B complete the remaining work?